BID RESULTS FOR THE OSWALT ACADEMY NEW CAMPUS PROJECT ARE IN – PRECISION NAILS THE INDEPENDENT CONSTRUCTION COST ESTIMATE
The bid results for the Oswalt Academy New Campus Project were recently announced. On May 28th 2020, the Rowland Unified School District provided a notice of intent to award a contract to ACC Contractors, Inc., for the construction of the new school campus located in Walnut, California.
As an extension of the design team, Precision served as the cost consultant for Ziemba + Prieto Architects, the architect of record. Our team provided multiple detailed construction cost estimates throughout the design process. We are proud to announce that Precision’s final construction cost estimate came within 2% of the average of the top three bids. See below for a full breakdown of the bid results along with our independent statement of probable construction cost.
BIDDERS | BID AMOUNT |
ACC Contractors, Inc. | $ 40,838,000 |
RC Construction Services, Inc. | $ 41,000,000 |
Precision Estimating Services | $ 41,296,095 |
Fast-Track Construction, Corp. | $ 44,500,000 |
Saifco Construction | $ 44,990,000 |
P.H. Hagopian Contractor, Inc. | $ 44,998,000 |
S.J. Amoroso | $ 49,877,000 |
Looking for a cost consultant to team with as a part of a design pursuit? Then click here for more information.